Harpeth Bend

Scenario comparison

MetricScheme A — 54-lot baseline

Baseline

Scheme B — 62-lot concept
Pad elevation (ft)633.5633.5
Est. lots5462
Storage compliancePASSPASS
Displaced storage (CY)54,85354,450
Effective comp storage (CY)89,05699,446
Storage surplus (CY)+23,232+34,106
Compacted yield (CY)64,56671,471
Fill required (CY)92,15491,476
Net balance (CY)-27,588-20,005
Import (CY)27,58820,005
Export (CY)00
Total earthwork cost$1,366,921$1,327,401
Cost per lot$25,313$21,410
Total lot value$6,480,000$7,440,000
Earthwork ROI (x)4.75.6
Warnings00